Expanding Our Home


What is the District’s plan to address activity and fine arts space needs? During the September 20, 2023, meeting, the Beresford School Board identified the following three large project focus areas/phases: 

  1. Activity Space Improvements (Gym Addition and MPR Remodel) by continuing to move forward to address our needs with a bond election;
    1. Bond Election in May of 2024
    2. Bid Project in December 2024
    3. Begin Construction in the Spring of 2025
    4. Utilize space during the 2025-2026 school year
  2. Fine Arts Space/Improvements (to begin improvements in 2033-2034) by saving Funds FY 2029 through FY 2033 and by engaging in conversations with key stakeholders regarding our intentions, efforts, and ideas in the fine arts; and 
  3. South Campus Lobby Improvements (to begin improvements in 2033-2034) by saving Funds FY 2030 through FY 2033. The District is calling a bond election to help finance the first phase of our strategic plan. 

The BSD BOE does not intend to seek additional bonds to address strategic priorities two and three.

For more information, go to buildingforberesford.com.